Projects

Gloucestershire Resource Centre

How the story began

The Gloucestershire Community Energy Co-operative (GCEC) started life in 2010 as FiVE Valleys energy Co-op, formed by a group of individuals who wished to install community based green energy systems in the Five Valleys area around Stroud. A few months after they were formed, Gloucestershire Resource Centre (GRC) – based at City Works in Gloucester – wanted to install solar photovoltaic panels but didn’t have the capital to fund the project. The GRC contacted The Solar Coop for advice on how to set up a community scheme to fund them. Kevin Frea from the Solar Coop called a meeting at GRC of relevant organisations in Gloucestershire that might be interested, which included representatives from FiVE and Transition Town Cheltenham.

The installation

Initially GCEC considered developing renewable energy installations at a number of sites throughout Gloucestershire.  However plans were scaled back to focus on the City Works installation when the Government announced that they were going to bring forward the deadline for reducing the Feed-in Tariff payment.  The Renewable Energy Co-operative who are also a South West based co-operative,  installed the 44.6 kWp solar photovoltaic system in December 2011, in time to meet the Feed-in Tariff deadline.  The array comprises 186 photovoltaic panels (each 240w), three SMA inverters as well as a public display.  The roof has a plain unshaded surface that extends 220 feet in length and faces south west.

Money

In order to get the installation completed and commissioned before the tariff change date, GCEC raised £105,000 in 3 weeks in short term loans from well wishers and supporters. They also negotiated a risk-share contract with the installer to mitigate against failing to meet the deadline.

In the spring of 2012 GCEC published its share prospectus, and the money raised through the share issue was used to pay off the loans.  The minimum investment was £240, and the maximum investment was £20,000. Many of those lending money converted some or all of their loan to investment. In less than two months the full sum was raised from local people who automatically became members of the Co-operative when they invested, with the aim of creating a more sustainable, ethical and local system of energy production.

There were 49 members who each subscribed to an average of just over £2000 of shares each, and almost everyone lived or worked in Gloucestershire.

The income from the Feed-in Tariff is used to pay interest to investors (at 5%), pay an income to Gloucestershire Resource Centre, the registered charity who own City Works, to help them become more sustainable, build a capital repayment fund to repay the original investments, and to administer these activities.

The FiT was initially paid at 32.9 p and is inflation proofed.

What is City Works?

The Gloucestershire Resource Centre (GRC) owns the City Works building where it delivers its Scrapstore service and hires out conference and art facilities. The Scrapstore diverts clean waste materials from local businesses to be reused as art, craft, play and educational resources by local groups and schools.  City Works is also a base for fourteen other social enterprises including Fair Shares and Co-operative Futures.

When City Works received their first quarterly electricity bill after the panels were installed it showed a reduction for the corresponding quarter from 12,630 to 7,720 kWh, suggesting that they’re using about half of the electricity produced.

Minchinhampton Primary Academy

Minchinhampton school after solar panel installation

Summary

Back in January 2017, current GCEC Board member, Matt Partridge, had an idea.  Noticing the large, south-facing roof at his children’s primary school in Minchinhampton, and well aware of the falling price of solar generation through his day job developing solar and wind farms, Matt made contact with the school about a potential solar roof project.

The following 5½ years involved taking the project through to its eventual installation in summer 2022.  Along the way, many challenges were successfully overcome, with enormous help from a dedicated and assorted team of “volunteers”!  Some of the main challenges are listed below (remembering that the over-arching COVID-19 pandemic challenge is excluded)!  Hopefully, the list will provide some useful information for other potential projects.

The project, in partnership with Diocese of Gloucester Academies Trust (the owner/operator of the school) is now providing electricity directly to the school at a cost that is expected to be significantly less than the school’s electricity tariff, while electricity from the solar roof not used by the school is exported to the local electricity grid.  The 51kWp system is expected to provide around half of the school’s electricity in a typical year while reducing annual carbon dioxide emissions by around 9 tonnes in its first year (by replacing electricity from power stations).

GCEC would welcome discussions with other schools about other potential projects.

CHALLENGES FACED and overcome

Roof structure – the technical/engineering drawings for the roofs were not available, so it was agreed that the conservative approach to this “unknown” was to adopt a design that avoided additional weight on the roof.  Hence, an in-roof solar system was adopted.  This had the benefit of a better aesthetic (particularly with the existing black roof tiles) but added to cost and marginally reduced generation.

Planning – many roof-top solar systems do not require planning permission, relying instead on permitted development (see: https://www.planningportal.co.uk/permission/common-projects/solar-panels/planning-permission-solar-equipment-mounted-on-a-house-or-a-block-of-flats-or-on-a-building).  However, because Minchinhampton Primary Academy is in a conservation area, planning permission was required.  Fortunately, achieving this was not contentious and a school governor kindly provided the necessary planning drawings via his planning practice (the planning fee was paid by the school; c. £200-300).

Funding – initially, the school hoped to secure an interest-free loan via the SALIX loan scheme, having previously secured funding in this way for a new boiler.  However, the loan application for the solar roof was not successful, but Matt knew about GCEC and had met a number of its directors.  A meeting between the school and GCEC was arranged which ultimately led to GCEC stepping in to fill this critical role.  GCEC then led on a successful community share offer securing the full £70,000 required to fund the project!

Grid connection – critically, Western Power Distribution was able to confirm its agreement to the installation of the project although export from the project is limited to 15kW (when the school is unable to use all the electricity being generated from the solar roof).

THANK YOUS

  • Nick Moss – Headteacher, Minchinhampton Primary Academy
  • Stephen Draper, Mark Catt, Robin Couling – Governors of Minchinhampton Primary Academy
  • Canon Rachel Howie and Rob Jones – Diocese of Gloucester Academies Trust
  • Solarsense – selected installer
  • The numerous private and business investors in the fully subscribed Community Share Offer

Minchinhampton Community Hub

This building provides a wide range of functions for the village, such as hosting meetings, toddler groups, and a fitness centre.  In 2022, the building managers were facing a challenge, in that the gas-fired hot air heating system was reaching the end of its life.  Given the need to respond to climate change and Net Zero commitments, an air-to-air heat pump system was a logical solution but would be more expensive to run given current gas and electricity prices.  This could be mitigated with a rooftop solar photovoltaic (PV) system to supply some of the extra electricity, but the total capital cost was unaffordable.

Fortunately, the management team at the Hub, led by Revd. Canon Howard Gilbert of Minchinhampton’s Holy Trinity church, were familiar with our project at the school, and enquired whether a similar deal could work for them.  The southerly orientation of the roof and absence of shading made it an attractive PV prospect, and being outside the village conservation area allowed permitted development criteria to apply, simplifying planning.   

A roof lease and power purchase contract was agreed in June 2023 under which the Hub would purchase electricity from the PV system installed by GCEC at a discounted rate for 25 years, and GCEC would contribute towards the capital cost of the heat pump system. A community fund raise was initiated immediately and achieved the target budget of £35,000 before the end of September. The system was installed late in October 2023, including air-to-air heat pumps, and has been fully operational since mid November.

Replacement of gas heating at the Hub has reduced the buildings previous carbon emissions of about 10 tons per year to a net figure (i.e. offsetting carbon emissions from grid electricity consumed with the benefit from PV exports displacing marginal gas fired generating plant) of about 0.6 ton. This residual figure will reduce as the carbon intensity of grid electricity falls, setting the Hub on a clear path to net zero.

A particular advantage of the air-to-air heat pumps installed is that they will provide air conditioning in summer, which is a valuable adaptation to the increasingly hot, and potentially dangerous, summers we can expect. The Hub will be able to act as a cool refuge for the village without placing much load on the grid thanks to the PV panels.